Precedence diagramming method: Some unusual characteristics and their implications for project managers

JOURNAL OF OPERATIONS MANAGEMENT · 1981
被引 82
人大 AFT50UTD24ABS 4*

中文导读

研究了前导图法(PDM)中开始-开始和完成-完成等新关系如何改变关键路径法的基本概念,包括关键路径、时差计算和工期压缩,并讨论了这些特性对项目经理和网络方法使用者的影响。

Abstract

Abstract The Precedence Diagramming Method, with its activity‐on‐node network and additional precedence relationships, offers an easier and more flexible network approach to modeling large projects than conventional PERT/CPM. But the new relationships (start‐to‐start and finish‐to‐finish constraints) can change some of the basic notions of critical path methodology, including the concept of a critical path itself. Calculations of early and late job start times are affected, along with total slack. Traditional methods of shortening a project by crashing jobs on the critical path can occasionally have anomalous effects. These little‐known characteristics of PDM are discussed, along with their implications for project managers, analysts, and other users of network methodology. Suggestions are made for improving the information available in computer printouts of PDM networks and for avoiding some of the anomalous effects. While PDM improves the project planner's ability to more simply and accurately model large projects, users should be aware of and able to effectively deal with its sometimes peculiar characteristics.

项目管理网络计划技术关键路径法运筹学