资源受限项目调度中的时间-资源权衡:非抢占情形

Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case

Management Science · 1982
被引 451 · 同刊同年前 5%
人大 A+FT50UTD24ABS 4*

中文导读

提出方法解决非抢占资源受限项目调度问题,其中每项任务工期取决于投入资源,支持多种目标函数(如最短工期、最低成本),并给出小问题最优解和大问题启发式解。

Abstract

This paper introduces methods for formulating and solving a general class of nonpreemptive resource-constrained project scheduling problems in which the duration of each job is a function of the resources committed to it. The approach is broad enough to permit the evaluation of numerous time or resource-based objective functions, while simultaneously taking into account a variety of constraint types. Typical of the objective functions permitted are minimize project duration, minimize project cost given performance payments and penalties, and minimize the consumption of a critical resource. Resources which may be considered include those which are limited on a period-to-period basis such as skilled labor, as well as those such as money, which are consumed and constrained over the life of the project. At the planning stage the user of this approach is permitted to identify several alternative ways, or modes, of accomplishing each job in the project. Each mode may have a different duration, reflecting the magnitude and mix of the resources allocated to it. At the scheduling phase, the procedure derives a solution which specifies how each job should be performed, that is, which mode should be selected, and when each mode should be scheduled. In order to make the presentation concrete, this paper focuses on two problems: given multiple resource restrictions, minimize project completion time, and minimize project cost. The latter problem is also known as the resource-constrained time-cost tradeoff problem. Computational results indicate that the procedures provide cost-effective optimal solutions for small problems and good heuristic solutions for larger problems. The programmed solution algorithms are relatively simple and require only modest computing facilities, which permits them to be potentially useful scheduling tools for organizations having small computer systems.

资源受限项目调度时间-资源权衡非抢占式多模式调度