可持续绿色施工管理:进度绩效与改进

SUSTAINABLE GREEN CONSTRUCTION MANAGEMENT: SCHEDULE PERFORMANCE AND IMPROVEMENT

Technological and Economic Development of Economy · 2014
被引 32
人大 A-

中文导读

研究了新加坡绿色建筑项目的进度绩效,发现比传统项目平均多花8%时间,且平均延误4.8%,并提出了改进建议,为行业提供基准参考。

Abstract

Over the last few years, the green building movement in Singapore has leaped bountifully. While environmental sustainability for greener construction has been emphasized, rare research has been conducted to analyze performance of green construction projects. As a result, this study aims to address schedule performance of green building construction projects and to provide some recommendations that may improve the targeted performance. To achieve this objective, a questionnaire was developed and the responses from 30 companies were analysed, and interviews with 6 project managers were conducted to further supplement and substantiate the survey results. The analysis reported that green building projects required an average of 8% more time than traditional building projects of similar size and characteristics. In addition, on average, these projects were delayed by 4.8% when compared with their as-planned schedules. Lastly, a list of recommendations was also introduced, aiming to ameliorate the schedule performance. This study will offer a benchmark for the industry to gauge the overall duration and performance of green building construction projects.

绿色建筑工期绩效新加坡施工管理