通过计划与订单审核/发布系统实现负载平滑:一项仿真实验

Load smoothing by the planning and order review/release systems: A simulation experiment

JOURNAL OF OPERATIONS MANAGEMENT · 1991
被引 56
人大 AFT50UTD24ABS 4*

中文导读

通过仿真实验,研究了制造计划系统的负载平滑功能与订单审核/发布机制对车间绩效的互补作用,发现两者结合能缩短交货时间、降低在制品库存并提高交付表现。

Abstract

Abstract Most research studies investigating the impact of Order Review/Release (ORR) mechanisms on shop performance have focused strictly on managing the flow of orders to the shop floor once they have been generated by the planning system. This approach ignores the possibility that the manufacturing planning system may be managing the incoming work flow so that peaks and valleys in the work load have been smoothed out. This study shows, via a simple computer simulation of a random job shop, that such smoothing by the planning system can improve system performance and enhance the effects of Order Review/Release. The two ‘filtering’ mechanisms of planning system smoothing and Order Review/Release have a complementary impact on the system, with smoothing working to reduce flow time and flow time variability and ORR working to reduce work in process and work in process variability. The combination of smoothing with ORR results in shorter and more consistent lead times, lower and more stable work‐in‐process levels and better delivery performance. This results in a system which is very stable and predictable. Further, the study shows that the combined effects of smoothing and ORR can improve the performance of simple shop floor dispatching rules like first come‐first served to the point where they are competitive with more sophisticated, due date oriented rules. This raises the possibility of simplifying control mechanisms on the shop floor by doing a better job of work load planning and order release.

生产计划订单管理车间调度仿真研究运营管理