Robust Resource Allocation Decisions in Resource‐Constrained Projects*

DECISION SCIENCES · 2007
被引 77
人大 AABS 3

中文导读

针对资源受限项目调度问题,研究了在活动工期不确定下如何分配资源以最大化基准调度方案的稳定性,提出了三种基于整数规划的启发式方法和一种构造性方法。

Abstract

ABSTRACT The well‐known deterministic resource‐constrained project scheduling problem involves the determination of a predictive schedule (baseline schedule or pre‐schedule) of the project activities that satisfies the finish–start precedence relations and the renewable resource constraints under the objective of minimizing the project duration. This baseline schedule serves as a baseline for the execution of the project. During execution, however, the project can be subject to several types of disruptions that may disturb the baseline schedule. Management must then rely on a reactive scheduling procedure for revising or reoptimizing the baseline schedule. The objective of our research is to develop procedures for allocating resources to the activities of a given baseline schedule in order to maximize its stability in the presence of activity duration variability. We propose three integer programming–based heuristics and one constructive procedure for resource allocation. We derive lower bounds for schedule stability and report on computational results obtained on a set of benchmark problems.

项目管理调度优化整数规划启发式算法