Better Estimation of PERT Activity Time Parameters
提出简单易用的近似公式来估计PERT活动时间的均值和方差,比现有PERT公式更准确,且只需三个概率点,能显著提高项目完工时间概率陈述的精度。
This paper builds upon earlier work from the decision/risk analysis area in presenting simple, easy-to-use approximations for the mean and variance of PERT activity times. These approximations offer significant advantages over the PERT formulas currently being taught and used, as well as over recently proposed modifications. For instance, they are several orders of magnitude more accurate than their PERT counterparts in estimating means and variances of beta distributions if the data required for all methods are obtained accurately. Moreover, they utilize probability data that can be assessed more reliably than those required by the PERT formulas, while still requiring just three points from each activity time probability distribution. Using the proposed approximations can significantly improve the accuracy of probability statements about project completion time, and their use complements ongoing efforts to improve PERT analyses of networks involving multiple critical paths.