流水线单元中考虑族类调整的排序规则与交货期设定程序

Sequencing rules and due date setting procedures in flow line cells with family setups

JOURNAL OF OPERATIONS MANAGEMENT · 1991
被引 22
人大 AFT50UTD24ABS 4*

中文导读

研究了流水线单元中考虑族类调整时的交货期设定与调度决策,发现交货期设定方式显著影响调度效果,并给出了不同情境下的最优规则组合。

Abstract

Abstract The purpose of this study is to investigate due date setting procedures and dispatching decisions in a flow line cell with family setups. In this environment, setups are not required when switching from a job in a given family to a job in the same family. However, switching from a job in one family to a job in another family requires a setup. Family setups in this shop are sequence independent. The dispatching decisions in this shop are threefold: (1) when should the decision to switch from one part family to another be made; (2) once the decision to switch families is made, how should the next part family be chosen (next family decision); and (3) how should the jobs within a family be prioritized (next job decision)? If the decision to switch classes can only be made after the current family is exhausted, the rule is called a class exhaustion rule. Otherwise the rule is a truncated rule. The results indicate that the due date setting procedure has a major impact on how dispatching should be performed in the shop. The family exhaustion procedure using the APT next family rule and the SPT next job rule is the best performer for mean flow time. When setup times are long, the SEQ due date rule using the family exhaustion procedure with the FCFS next family and the EDD next job rules performed well for due date criteria. When setup times are short, the EDD/T, Sawicki truncation rule and the family exhaustion rules performed well for due date criteria.

生产调度运营管理交货期设定排序规则