串行生产系统中考虑拖期成本的计划提前期设定

Setting Planned Leadtimes in Serial Production Systems with Tardiness Costs

Management Science · 1987
被引 154
人大 A+FT50UTD24ABS 4*

中文导读

研究串行生产系统中如何确定最优计划提前期,以最小化库存持有成本和拖期成本之和,提出了两阶段系统的单次求解算法并推广到多阶段。

Abstract

We investigate the problem of determining optimal planned leadtimes in serial production systems in which the actual procurement and processing times may be stochastic. The objective is to minimize the sum of inventory holding costs and job tardiness costs given a customer specified due-date. We present a general solution procedure for two stage serial systems, which for most cost structures and leadtime distributions is a single-pass algorithm. We also indicate how the procedure can be extended to N-stage systems. We present computational results which provide some insight into the characteristics of optimal safety time policies.

计划提前期串行生产系统延期成本安全时间