中文导读

研究在资源约束的项目中,通过灵活资源分配来缩短工期的问题,开发了接近最优的启发式算法,并实验发现资源灵活性均匀分布时,少量改进即可带来与完全灵活系统相近的工期收益。

Abstract

We consider the problem of minimizing project duration in an environment where each project activity can be executed by a number of different flexible resources. The capabilities of the flexible resources are modeled using a binary activity-resource matrixAcalled theavailabilitymatrix. Activity durations are known deterministically. We develop tight lower bounds and a variety of heuristics accompanied with extensive computational tests regarding their performance. It is shown that our algorithms consistently perform near optimally. Using these heuristics, we perform experiments on the effect of operating flexibility on project duration, where resource flexibility is measured by the number of resources available per activity, and the form of the availability matrixA. Our experiments lead to important managerial guidelines regarding the role of resource flexibility on project duration. For instance, it is found that when the flexible capabilities of the resources are evenly distributed across the activities, small improvements in resource flexibilities provide nearly the same benefits in project duration as a system of fully flexible resources.

资源柔性项目工期资源约束任务分配可用性矩阵