批量大小、提前期与在制品库存

Lot Sizes, Lead Times and In-Process Inventories

Management Science · 1987
被引 456 · 同刊同年前 6%
人大 A+FT50UTD24ABS 4*

中文导读

研究批量制造车间中批量大小与提前期的关系,及其对在制品库存的影响,帮助管理者理解并优化生产决策。

Abstract

In many manufacturing problems, the total lead time taken to manufacture a product is an important consideration. Long lead times impose costs due to higher work-in-process inventory, increased uncertainty about requirements, larger safety stocks and poorer performance to due dates. Traditional lot sizing models ignore lead time related costs, although there are systematic relationships between lot sizes and lead times. This paper examines these relationships and their implications for lot sizing and work-in-process inventories, for batch manufacturing shops with queues.

批量大小提前期在制品库存