连续时间下的产能扩张项目排序问题

Sequencing Capacity Expansion Projects in Continuous Time

Management Science · 1986
被引 16
人大 A+FT50UTD24ABS 4*

中文导读

研究在给定时间范围内,如何排序不同容量和成本的产能扩张项目,以最低成本满足连续需求,并提出了分支定界法和启发式算法。

Abstract

We consider a problem of sequencing capacity expansion projects with a continuous demand function specified over a given time horizon. Each type of expansion project has a specified integer capacity and an associated cost which is nonincreasing with respect to the time at which the project is brought on stream. The problem is to determine the sequence of expansions to provide sufficient capacity to meet demand at minimum cost. A formulation is presented and its relaxation leads to a shortest route problem. The sequencing problem is solved using a branch and bound procedure with Lagrangean relaxation providing bounds. A particularly effective heuristic is also developed. Computational results are given.

产能扩张项目排序连续时间拉格朗日松弛