考虑工人差异和加班成本的同步非节拍流水线

Synchronous Unpaced Flow Lines with Worker Differences and Overtime Cost

Management Science · 2000
被引 28
人大 A+FT50UTD24ABS 4*

中文导读

研究如何为不同技能的工人分配任务和工位,以最小化正常工时和加班成本之和,发现计划加班常有益,且工人差异增大时应多招人。

Abstract

In this paper, we consider the design of a synchronous, unpaced flow line where workers operate at different skill levels and overtime is used, if necessary, to meet a daily production quota. The line is unpaced in the sense that items only move to the next workstation when all workers on the line have completed their respective tasks. The design problem in this case is to assign both workers and tasks to workstations to minimize the expected sum of regular and overtime costs. To solve this problem, we develop an optimization algorithm for smaller problems and a heuristic algorithm for larger problems, which we use to investigate the sensitivity of total expected cost to changes in the price of overtime, hiring practices, worker differences, and the overall amount of work time variability. Based on an extensive computational analysis, we found that (1) planned overtime is frequently beneficial, (2) more workers should be hired as worker variability increases, and (3) increases in overtime costs frequently yield a relatively lower percentage increase in total expected cost. Other managerial implications are discussed in the paper.

同步流水线工人技能差异加班成本任务分配优化