改进巴基斯坦铁路控制系统测试系统

IMPROVING A RAILWAY CONTROL TEST SYSTEM IN PAKISTAN

JOURNAL OF SUPPLY CHAIN MANAGEMENT · 2014
被引 0
人大 A-ABS 4

中文导读

研究一家国际铁路控制方案公司在巴基斯坦的铁路信号项目中,因控制柜测试失败导致延误和成本增加,运用六西格玛方法将故障率降至合同容忍目标,提升项目效率。

Abstract

The focus company is an international Rail Control Solution firm. It has a contract for providing a modern railway signaling system in Pakistan. Significant delays have prolonged the implementation and increased costs. One cause is the testing failure of the Controller Cabinet, and this research concentrates on that. Six-Sigma methodology is used, with its five phases: define, measure, analyze, improve, and control. The five phases stimulate improvement in the work process, the project’s deliverable performance, and quality assurance, which lead to project efficiency and cost effectiveness. The failure rate is reduced to the contract tolerance target. The implementation of these improvements could bring success to the firm’s cabinet start-up test, and thus remove the delays and costs.

铁路信号六西格玛项目管理质量控制系统工程