基于信息流交互的关键链项目缓冲确定

Determination of critical chain project buffer based on information flow interactions

Journal of the Operational Research Society · 2016
被引 22
ABS 3

中文导读

提出一种基于活动间信息流交互计算返工安全时间的方法,通过设计结构矩阵优化关键链排序,再用尾部集中法确定项目缓冲,相比传统方法能缩短工期、降低成本并提高按时完工率。

Abstract

It has been well accepted in the literature that co-dependency between project activity durations is caused by resource tightness and network complexity. However, we show that information flow interaction between activities is the key factor for it. Based on whether there exist spliced relationships between activities, we introduce the concept of rework safety time. We propose a method to compute the rework safety time using the information output and input time factors, rework probability matrix, and rework impact matrix. We achieve the optimization of the critical chain sequencing via the design structure matrix so that the dependency between activities is reduced. The project buffer is then determined by the tail concentration method based on the optimized chain. The empirical results show that, as opposed to the traditional RSEM method, our approach improves the project buffer consumption rate, shortens project duration, reduces project cost, and increases project on-time completion rate.

项目管理关键链缓冲管理设计结构矩阵返工