公共基础设施项目的成本绩效:变更单的宿敌与涅槃

Cost performance of public infrastructure projects: the nemesis and nirvana of change-orders

Production Planning and Control · 2017
被引 61
ABS 3

中文导读

研究发现公共基础设施项目合同签署后的变更单平均导致成本增加23.75%,且变更单增加与承包商利润率正相关,纳税人承担额外成本,承包商获利。

Abstract

The cost performance of a wide range of public sector infrastructure projects completed by a contractor are analysed and discussed. Change-orders after a contract to construct an asset was signed were, on average, found to contribute to a 23.75% increase in project costs. A positive association between an increase in change orders and the contractor’s margin were identified. Taxpayers pay for this additional cost, while those charged with constructing assets are rewarded with an increase in their margins. As the public sector embraces an era of digitisation, there is a need to improve the integration of design and construction activities and engender collaboration to ensure assets can be delivered cost effectively and future-proofed. The research paper provides empirical evidence for the public sector to re-consider the processes that are used to deliver their infrastructure assets so as to reduce the propensity for cost overruns and enable future-proofing to occur.

公共基础设施项目管理成本超支变更单公共部门