具有学习效应、共同交货期和可控加工时间的无等待双机排列流水车间调度问题

No-wait two-machine permutation flow shop scheduling problem with learning effect, common due date and controllable job processing times

International Journal of Production Research · 2017
被引 42
ABS 3

中文导读

研究双机无等待排列流水车间中,如何同时决定共同交货期、资源分配和工件顺序,以最小化提前、延误、交货期和资源总成本,并证明该问题可在多项式时间内求解。

Abstract

We consider a two-machine no-wait permutation flow shop common due date assignment scheduling problem where the processing time of a job is given as a function of its position in the sequence and its amount of resource allocated to this job. The common due date (CON) assignment method means that all the jobs are given a common due date. We need to make a decision on the common due date, resource allocation and the sequence of jobs to minimise total earliness, tardiness, common due date cost and total resource cost. We show that the problem remains polynomially solvable under the proposed model.

调度优化生产调度运筹学流水车间调度