多生产线预制构件生产重调度的需求变动动态响应

Dynamic response to demand variability for precast production rescheduling with multiple lines

International Journal of Production Research · 2018
被引 58
ABS 3

中文导读

针对预制构件生产中需求变动问题,提出基于遗传算法的两层次重调度模型,通过生产线选择和任务重排最小化成本,案例显示可节省58.1%和48.5%的成本。

Abstract

Production scheduling plays a crucial role in the prefabricated construction productivity and on-time delivery of precast components (PCs). However, previous studies mainly focused on the static scheduling of single production line without considering the demand variability in practice. To achieve dynamic production planning, a Two-level Rescheduling Model for Precast Production with multiple production lines is developed to minimise the rescheduling costs based on genetic algorithm, from the two levels of (1) selection of production line and (2) rescheduling of jobs based on PCs’ priority. Further, two scenarios of different and shared mould types are investigated to represent real-world production environments. Finally, a real case study is conducted to test the validity of proposed rescheduling model. 58.1 and 48.5% cost savings are achieved by comparison to no response to changes and heuristic rescheduling methods, respectively. This research contributes to the precast production theory by expanding the insight into dynamic rescheduling with multiple production lines. The methodology will promote the on-time delivery of PCs and enhance the dynamic precast production management.

预制建筑生产调度运筹学土木工程遗传算法