Optimal order release dates for two-level assembly systems with stochastic lead times at each level
研究了在随机提前期下,两级装配系统中组件补货的优化问题,通过遗传算法确定订单释放日期以最小化总期望成本,对运营管理者和供应链研究者有参考价值。
In this paper, we examine an optimisation problem for component replenishment in two-level assembly systems under stochastic lead times. The Assembly-to-Order principle is applied. The demand for a finished product and its planned due date are known. The capacity of the assembly system at each level is considered infinite. At each level, the assembly process starts when all the required components or semi-finished items are available. At the second level, the components are ordered from external suppliers and order release dates are decision variables of the problem. A backlogging cost is incurred if the finished product demand is satisfied after the planned due date. If the finished product, a given component or a semi-finished product is available before the corresponding assembly date, an inventory holding cost is considered. Genetic algorithms (GA) reinforced with different techniques are developed to find order release dates that minimise the total expected cost. A Branch and Bound method is also developed to assess the effectiveness of the hybrid GA. Regardless of the number of components and the variability of the costs related to the finished product, the experimental results indicate that the proposed GA are highly efficient.