移动瓶颈方法中的机器关键性度量与子问题求解过程:一项计算研究

Machine Criticality Measures and Subproblem Solution Procedures in Shifting Bottleneck Methods: A Computational Study

Journal of the Operational Research Society · 1996
被引 0
ABS 3

中文导读

研究了不同机器关键性度量和子问题求解过程对移动瓶颈方法在最小化作业车间最大延迟问题上的性能影响,发现平衡负载和随机路径下简单方法即可,路径结构影响显著。

Abstract

AbstractWe examine the effects of different machine criticality measures (MCMs) and subproblem solution procedures (SSPs) on the performance of Shifting Bottleneck (SB) methods for the problem of minimizing maximum lateness in a job shop. Extensive computational experiments show that for problems with balanced workloads and random routeings simple MCMs and SSPs can be used without affecting solution quality. Routeing structure affects the performance of the SB method significantly. We also find that, contrary to some previous studies, the problem of maintaining feasibility in the SB method is significant.Keywords: schedulingheuristicscomputational analysis

生产调度运筹学启发式算法计算分析