Project Management Duration/Resource Tradeoff Analysis: an Application of the Cut Search Approach

Journal of the Operational Research Society · 1996
被引 0
ABS 3

中文导读

提出一种基于割搜索方法的网络程序,用于在假设线性资源利用函数下,以最小额外资源消耗将项目工期从正常压缩至极限,帮助项目经理在工期与资源间做出权衡。

Abstract

The paper presents an application oriented procedure for solving the project management duration/resource tradeoff problem. A procedure is presented for reducing a project from a normal to a crash duration state at a minimum amount of additional resource expenditure assuming a linear utilization functions. The procedure is network based using a graphical Cut Search Approach to locate the minimal resource level at each reduction in total project duration. Activity-on-arc networks and flow networks are utilized. The paper is presented for practical application and for conceptual development as compared to a theoretical treatment.