加工时间线性依赖于作业等待时间的两机器流水车间调度问题

Scheduling of a Two-machine Flowshop with Processing Time Linearly Dependent on Job Waiting-time

Journal of the Operational Research Society · 1989
被引 2
ABS 3

中文导读

研究了两机器流水车间中加工时间随等待时间线性变化的调度问题,证明了其NP难性,并提出了一个启发式算法及其最坏情况界。

Abstract

This paper deals with the problem of finding the minimum finish-time schedule in a two-machine flowshop, where the processing times of jobs are linearly dependent on the job waiting-times. The problem is shown to be NP-hard. A heuristic algorithm is presented, and the worst-case bounds are derived for the different variations of the algorithm.

调度理论流水车间计算复杂性启发式算法