多技能资源受限项目调度问题的分类与新基准实例

A classification and new benchmark instances for the multi-skilled resource-constrained project scheduling problem

European Journal of Operational Research · 2022
被引 54 · 同刊同年前 10%
ABS 4

中文导读

研究了多技能资源受限项目调度问题,提出新的分类方案和数据生成方法,并创建了多个人工数据集,通过与软件和铁路公司的实际案例对比验证其质量。

Abstract

This paper studies and analyses the multi-skilled resource-constrained project scheduling problem (MSRCPSP). We present a new classification scheme based on an existing classification scheme for project scheduling problems. This allows researchers to classify all multi-skilled project scheduling problems and its extensions. Furthermore, we propose a new data generation procedure for the MSRCPSP and introduce multiple artificial datasets for varying research purposes. The new datasets are generated based on new multi-skilled resource parameters and are compared to existing benchmark datasets in the literature. A set of 7 empirical multi-skilled project instances from software and railway construction companies are collected in order to validate the quality of the artificial datasets. Solutions are obtained through a genetic algorithm and by solving a mixed-integer linear programming formulation with CPLEX 12.6. The hardness of the multi-skilled project instances is investigated in the computational experiments. An experimental analysis studies the impact of skill availability, workforce size and multi-skilling on the makespan of the project.

项目调度运筹优化多技能资源基准测试