模块化集成建筑中模块的运输调度

Transportation scheduling for modules used in modular integrated construction

International Journal of Production Research · 2023
被引 33
ABS 3

中文导读

针对模块化集成建筑运输成本高的问题,建立整数规划模型优化调度,以香港数据验证可降低58.7%成本,对建筑从业者具有经济价值。

Abstract

Modular integrated construction (MiC) is an innovative construction method that is widely used in practice, but high transportation cost is an obstacle to its wider implementation. This paper is motivated by the real-world need for a scientific approach for MiC transport scheduling, and addresses the practical problem of how to achieve on-time door-to-door MiC delivery in an economical manner. An innovative integer programming model is formulated with the objective of minimising the total transportation costs, including trailer rental, fuel costs, and worker salaries. A case study based on Hong Kong data validates that the developed model can be efficiently solved for problems of practical size. The results also demonstrate that the derived MiC schedule plan can reduce transportation costs by 58.7% compared with a just-in-time (JIT) strategy, thus bringing great economic benefits to off-site construction practitioners. Useful managerial implications related to on-site MiC storage areas are derived through sensitivity analysis. Overall, this paper sets the ground for the application of mathematical programming methodology to the off-site construction field. Future research may be devoted to MiC transport scheduling under uncertainty.

模块化建筑运输调度整数规划建筑管理运筹学