具有爬坡速率限制的风电场储能系统建模:一种半马尔可夫调制布朗桥方法

Modelling a storage system of a wind farm with a ramp-rate limitation: a semi-Markov modulated Brownian bridge approach

Annals of Operations Research · 2024
被引 0
ABS 3

中文导读

提出一种新方法,模拟风电场运营商因违反爬坡速率限制政策而受到的惩罚,通过半马尔可夫过程建模电池充放电状态,并用修正布朗桥描述能量变化,基于十年真实数据验证模型有效性。

Abstract

Abstract We propose a new methodology to simulate the discounted penalty applied to a wind-farm operator by violating ramp-rate limitation policies. It is assumed that the operator manages a wind turbine plugged into a battery, which either provides or stores energy on demand to avoid ramp-up and ramp-down events. The battery stages, namely charging, discharging, or neutral, are modeled as a semi-Markov process. During each charging/discharging period, the energy stored/supplied is assumed to follow a modified Brownian bridge that depends on three parameters. We prove the validity of our methodology by testing the model on 10 years of real wind-power data and comparing real versus simulated results.

风电场储能系统爬坡速率限制半马尔可夫过程布朗桥