基于综合属性与活动偏好的关键链项目缓冲监控

Critical chain project buffer monitoring based on integrated attributes and activity preferences

Journal of the Operational Research Society · 2025
被引 2
ABS 3

中文导读

提出一种结合活动工期、成本和质量属性的缓冲分配方法,并根据活动偏好实施差异化监控策略,通过案例和蒙特卡洛模拟验证了该方法能同时优化项目工期和成本,为管理者应对不确定性提供决策支持。

Abstract

The complex external environment and idiosyncratic activities make monitoring variability throughout the project more challenging. To establish a reasonable and effective buffer monitoring method, this study synthesizes activity duration-cost-quality attributes for buffer allocation and implements different buffer monitoring strategies through activity preferences. First, the comprehensive activity attributes are determined by considering the activity duration, cost, and quality attributes, and the buffer is allocated in a decentralized-centralized manner based on the comprehensive attributes. Second, different buffer monitoring points and ways are determined based on the allocated buffers. Finally, the buffer monitoring model is simulated and validated by a case study on the integrated optimization of overall project performance. Compared to the classical static trisection and cumulative dynamic monitoring methods, Monte Carlo results show that this method achieves the dual optimization of project duration and cost. It effectively improves the comprehensive performance of buffer monitoring. Through in-depth analysis of activity attributes and the construction of differentiated buffer monitoring models, this study offers quantitative decision support to managers in coping with uncertainty perturbations, while also enriching the body of knowledge on differential buffer monitoring within the critical chain.

项目管理关键链缓冲监控项目调度运筹学