核电站退役成本估算中的应急费用

Contingency in nuclear power plant decommissioning cost estimation

Energy Economics · 2025
被引 3
人大 A-ABS 3

中文导读

研究了核电站退役成本估算中应急费用的确定方法,提出考虑活动成本相关性的模拟模型,并应用于美国Kewaunee核电站的退役成本估算。

Abstract

Hundreds of estimates have been made of decommissioning costs for commercial nuclear power plants. There is no standard method for making these estimates, particularly for estimating contingency, a type of risk premium, to cover unexpected costs during project execution. Following cost engineering guidelines for estimating contingency requires, among other project characteristics, consideration of (1) the cost estimate's probability distribution, (2) the cost estimate's variance, (3) the estimator's assumed accuracy range that will contain the final cost, (4) the estimator's level of confidence that the final cost will be in the stated accuracy range, and (5) the cost estimate user's risk aversion. The variance (or standard deviation) can be calculated using Monte Carlo techniques, which generally assume no correlation between individual activity costs. Because of portfolio effects, the simulated standard deviation of the aggregated activity cost is smaller than what would be suggested by nuclear decommissioning cost estimating guidelines. The simulated standard deviation is more reasonable when correlations are assumed to be non-zero between activities. This conclusion is shown by applying the proposed method for estimating contingency to activity costs estimated by the decommissioning operations contractor Energy Solutions to decommission the Kewaunee nuclear power plant in Wisconsin, while it is decommissioning four other US nuclear power units after it completed the decontamination and demolition of four units, including Zion 1&2. Energy Solutions could be approaching Nth-of-a-Kind decommissioning costs for US nuclear power plants, thus cost uncertainty should decrease. • The US is approaching Nth-of-a-Kind nuclear power plant decommissioning costs. • The uncertainty in the cost of decommissioning US nuclear power plants should decline. • Cost contingency is a function of variance, accuracy, confidence, and risk aversion. • A simulated cost estimate should include correlations among project activity costs. • The proposed contingency (risk premium) model mimics cost engineering guidelines.

核电站退役成本估算应急费用蒙特卡洛模拟